Beach 108th Street Esplanade Reconstruction

Project Timeline

Design

Start Date: March 2019
Projected Completion Date: September 2020

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal

At this rate, it may be completed by Spring 2023

Here’s the latest according to the Parks department:

Design is 80% complete and the parks staff members are reviewing construction documents for this project.

promenadetimeline

Two weeks away from March. Is this project delayed yet again?