Beach 24th and 25th Streets Ramps Construction

Project Timeline

Design

Start Date: April 2018
Projected Completion Date: October 2019
Completion Date: August 2020

Procurement

Start Date: August 2020
Projected Completion Date: May 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $1 million and $3 million
Funding Source: Federal