Broad Channel Park Reconstruction

Project Timeline

Design

Start Date: October 2017
Projected Completion Date: April 2019
Completion Date: February 2019

Procurement

Start Date: February 2019
Projected Completion Date: November 2019
Adjusted Completion Date: February 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:

  • Borough President
  • City Council