Rockaway Beach Skate Park Reconstruction

Project Timeline

Design

Start Date: March 2015
Projected Completion Date: April 2016
Completion Date: January 2018

Procurement

Start Date: January 2018
Projected Completion Date: October 2018
Completion Date: July 2019

Construction

Start Date: September 2019
Projected Completion Date: December 2020
Completion Date: October 2020

Funding

Total Funding: $3,538,000
Funding Sources:

  • Mayoral
  • Borough President
  • Federal