Rockaway Community Park Reconstruction

Project Timeline

Design

Start Date: December 2018
Projected Completion Date: June 2020
Adjusted Completion Date: August 2021

Procurement

The average time for procurement is 9 months. The procurement timeline for this specific contract will be established at the conclusion of the design phase.

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Greater than $10 million
Funding Source: Federal