Shore Front Parkway Adventure Course Construction

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Adjusted Completion Date: April 2021

Bid Due Date: 03/13/2020 10:30 am

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $3 million and $5 million
Funding Sources:

  • Mayoral
  • Borough President
  • City Council
  • Federal
Engineer’s Estimate $3,428,346.87
William A Gross Construction Associates, Inc. $3,294,000.00
JCC CONSTRUCTION CORP. $3,433,333.00
Doyle-Baldante, Inc. $3,709,681.00
Verdugos General Contractors Corp $3,742,950.10
Padilla Construction Services Inc $4,172,109.00
St John Enterprises $4,214,451.35
Rocco Agostino Landscape & General Contractor Corp. $4,448,000.00
AAH Construction $4,593,385.00