Shore Front Parkway Beach 98th Playground Construction

Project Timeline

Design

Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: October 2019

Procurement

Start Date: October 2019
Projected Completion Date: July 2020
Adjusted Completion Date: March 2021

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $5 million and $10 million
Funding Sources:

  • Mayoral
  • Borough President
  • Federal

Here’s the latest according to the Parks department:

Procurement is 40% complete

The procurement completion date has changed. Some of the common reasons why a completion date has changed are: the vendor, project and/or contract documents are under review, the agency is securing additional funding to award, or it was in the City’s best interest to extend the bid opening date.

At this rate, it may be completed by Spring 2023