Shore Front Parkway Dog Run Construction

Design

Start Date: January 2018
Projected Completion Date: July 2019
Completion Date: August 2019

Procurement

Start Date: August 2019
Projected Completion Date: May 2020
Adjusted Completion Date: March 2021

Bid Due Date: 02/25/2020 10:30 am

Construction

The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.

Funding

Total Funding: Between $1 million and $3 million
Funding Sources:

  • Mayoral
  • Borough President
  • Federal
Engineer’s Estimate $1,243,818.84
RMZ Contracting Inc. $765,000.00
St. John Enterprises, Inc. $1,531,766.78
William A. Gross Construction Assoc., Inc. $1,543,000.00
Verdugos General Contractors Corp $1,637,366.38
AMB Contractors, Inc. $1,851,650.40
AAH Construction $1,861,954.00
JCC CONSTRUCTION CORP. $1,890,593.00
MSM EMPIRE CONSTRUCTION CORP $1,891,235.00
Jaysan Contracting Corp $2,327,015.00
Fidelis Contracting Inc. $2,782,460.00