Project Timeline
Design
Start Date: March 2018
Projected Completion Date: September 2019
Completion Date: October 2019
Procurement
Start Date: October 2019
Projected Completion Date: July 2020
Adjusted Completion Date: April 2021
Construction
The average time for construction is 12-18 months. The construction timeline for this specific contract will be established at the conclusion of the procurement phase.
Funding
Total Funding: Between $1 million and $3 million
Funding Sources:
- Mayoral
- Borough President
- City Council
- Federal